Highfield Farm
REPD record 1685. Status: Revised.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 17 MW
- Status
- Revised
- Operator
- Denis Sharpe
- County
- Lincolnshire
- Region
- East Midlands
- Country
- England
- Planning authority
- South Kesteven
- Planning reference
- S13/2132
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2014-04-25
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-08-28: Planning Application Submitted
- 2014-03-12: Planning Application Withdrawn
Open this area on the map