slava.energy: UK renewable energy projects
Smiddyhill, Strichen - Battery Energy Storage
REPD record 16884. Status: Planning Application Submitted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 49.9 MW
- Status
- Planning Application Submitted
- Operator
- Muirden Energy
- County
- Aberdeenshire
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Aberdeenshire
- Planning reference
- APP/2024/1770
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-12-10
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-10-31: Planning Application Submitted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 16884. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.