slava.energy: UK renewable energy projects
Titchfield Lane, Wickham - Battery Energy Storage System
REPD record 16984. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- not held by REPD
- Status
- Planning Permission Granted
- Operator
- Grenergy Renewables
- County
- Hampshire
- Region
- South East
- Country
- England
- Planning authority
- Winchester
- Planning reference
- 24/02818/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-03-31
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-01-03: Planning Application Submitted
- 2026-03-27: Planning Permission Granted
- 2029-03-27: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 16984. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.