Goose Willow Farm
REPD record 1716. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 11.5 MW
- Status
- Operational
- Operator
- IKAROS SOLAR LIMITED
- County
- Oxfordshire
- Region
- South East
- Country
- England
- Planning authority
- Vale of White Horse
- Planning reference
- P12/V2112/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2014-02-28
Status history
Dated status events as published by REPD, release Q3 2026.
- 2011-12-11: Planning Permission Expired
- 2012-10-18: Planning Application Submitted
- 2012-12-11: Planning Permission Granted
- 2013-07-31: Under Construction
- 2013-12-23: Operational
Open this area on the map
Other REPD records on the same site
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1716. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.