slava.energy: UK renewable energy projects
Newnham Farm
REPD record 1722. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 2 MW
- Status
- Planning Permission Expired
- Operator
- Low Carbon Solar (Liquidated)
- County
- Isle of Wight
- Region
- South East
- Country
- England
- Planning authority
- Isle of Wight
- Planning reference
- P/00338/11
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-07-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 2011-03-21: Planning Application Submitted
- 2011-05-20: Planning Permission Granted
- 2016-05-20: Planning Permission Expired