Sevor Farm
REPD record 1724. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 9.3 MW
- Status
- Operational
- Operator
- AEE Renewables
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Swindon
- Planning reference
- S/13/0165
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2014-02-18
Status history
Dated status events as published by REPD, release Q3 2026.
- 2011-05-28: Planning Permission Expired
- 2013-02-11: Planning Application Submitted
- 2013-05-28: Planning Permission Granted
- 2013-09-30: Under Construction
- 2013-11-30: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1724. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.