Great Oak Energy Hub
REPD record 17245. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 400 MW
- Status
- Planning Permission Granted
- Operator
- Clearstone Energy Limited
- County
- West Sussex
- Region
- South East
- Country
- England
- Planning authority
- Horsham
- Planning reference
- DC/24/1289
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-05-06
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-09-17: Planning Application Submitted
- 2025-03-28: Planning Permission Granted
- 2030-03-28: Planning Permission Expired