slava.energy: UK renewable energy projects
Riverside Park Industrial Estate - Battery Energy Storage
REPD record 17302. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 0.2 MW
- Status
- Planning Permission Granted
- Operator
- AMP Clean Energy
- County
- Cleveland
- Region
- North East
- Country
- England
- Planning authority
- Middlesbrough
- Planning reference
- 24/0384/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-06-17
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-09-24: Planning Application Submitted
- 2025-05-23: Planning Permission Granted
- 2028-05-22: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 17302. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.