slava.energy: UK renewable energy projects

BESS Facility Development in Killeter

REPD record 17420. Status: Planning Application Withdrawn.

Facts

As published by REPD, release Q3 2026.

Technology
Battery
Capacity
82 MW
Status
Planning Application Withdrawn
Operator
Green Frog Power (Gort BESS) Limited
County
Strabane
Region
Northern Ireland
Country
Northern Ireland
Planning authority
Derry City and Strabane
Planning reference
LA11/2024/0745/F
Turbines
not held by REPD
Turbine size
not held by REPD
Record last updated in REPD
2025-08-05

Status history

Dated status events as published by REPD, release Q3 2026.

Open this area on the map

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 17420. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.