slava.energy: UK renewable energy projects
BESS Facility Development in Killeter
REPD record 17420. Status: Planning Application Withdrawn.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 82 MW
- Status
- Planning Application Withdrawn
- Operator
- Green Frog Power (Gort BESS) Limited
- County
- Strabane
- Region
- Northern Ireland
- Country
- Northern Ireland
- Planning authority
- Derry City and Strabane
- Planning reference
- LA11/2024/0745/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-08-05
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-09-20: Planning Application Submitted
- 2025-06-26: Planning Application Withdrawn
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 17420. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.