slava.energy: UK renewable energy projects
Fosse Way - Battery Storage
REPD record 17430. Status: Appeal Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- not held by REPD
- Status
- Appeal Granted
- Operator
- Staffordshire Solar 1 Limited
- County
- Warwickshire
- Region
- West Midlands
- Country
- England
- Planning authority
- Warwick
- Planning reference
- W/24/1404
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-08-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-10-15: Planning Application Submitted
- 2025-05-22: Planning Permission Refused
- 2026-05-14: Appeal Granted
- 2026-05-14: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 17430. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.