slava.energy: UK renewable energy projects
Haughton Park Farm, West Drayton - Photovoltaic Panel Arrays
REPD record 17492. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.15 MW
- Status
- Planning Permission Granted
- Operator
- Thaymar Limited
- County
- Nottinghamshire
- Region
- East Midlands
- Country
- England
- Planning authority
- Bassetlaw
- Planning reference
- 24/01225/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-01-13
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-10-30: Planning Application Submitted
- 2024-12-24: Planning Permission Granted
- 2027-12-24: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 17492. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.