slava.energy: UK renewable energy projects
New Rendy Farm
REPD record 1750. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 4.8 MW
- Status
- Operational
- Operator
- TGC Renewables
- County
- Somerset
- Region
- South West
- Country
- England
- Planning authority
- Somerset
- Planning reference
- 27/13/0003
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2014-03-24
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-03-05: Planning Application Submitted
- 2013-05-29: Planning Permission Granted
- 2013-12-15: Operational
- 2015-05-29: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1750. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.