slava.energy: UK renewable energy projects
Stallingborough Road - Battery Storage
REPD record 17509. Status: Planning Application Submitted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 125 MW
- Status
- Planning Application Submitted
- Operator
- Island Green Power
- County
- Lincolnshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- West Lindsey
- Planning reference
- WL/2025/00667
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-08-14
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-07-02: Planning Application Submitted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 17509. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.