Copley Farm
REPD record 1752. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 30 MW
- Status
- Operational
- Operator
- TGC Renewables
- County
- Lincolnshire
- Region
- East Midlands
- Country
- England
- Planning authority
- South Kesteven
- Planning reference
- S13/3273
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-03-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-01-13: Planning Application Submitted
- 2014-04-24: Planning Permission Refused
- 2014-05-16: Appeal Lodged
- 2015-01-06: Appeal Granted
- 2015-01-06: Planning Permission Granted
- 2015-06-28: Under Construction
- 2016-01-13: Operational
- 2018-01-06: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1752. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.