Kings Dyke, Whittlesey - Battery Energy Storage
REPD record 17656. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 10 MW
- Status
- Planning Permission Granted
- Operator
- Power Initiatives Limited
- County
- Cambridgeshire
- Region
- Eastern
- Country
- England
- Planning authority
- Fenland
- Planning reference
- F/YR24/0932/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-05-12
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-11-19: Planning Application Submitted
- 2025-05-02: Planning Permission Granted
- 2028-05-02: Planning Permission Expired