Euston Way - Energy Storage Facility
REPD record 17676. Status: Planning Application Withdrawn.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 0.2 MW
- Status
- Planning Application Withdrawn
- Operator
- AMP Clean Energy
- County
- Shropshire
- Region
- West Midlands
- Country
- England
- Planning authority
- Telford and Wrekin
- Planning reference
- TWC/2024/0836
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-02-10
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-11-13: Planning Application Submitted
- 2024-12-12: Planning Application Withdrawn
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 17676. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.