Southwick Estate
REPD record 1768. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 48 MW
- Status
- Operational
- Operator
- Bluefield Solar Income Fund
- County
- Hampshire
- Region
- South East
- Country
- England
- Planning authority
- Winchester
- Planning reference
- 13/02304/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-03-17
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-10-16: Planning Application Submitted
- 2013-12-13: Planning Permission Granted
- 2014-12-10: Under Construction
- 2015-03-10: Operational
Open this area on the map