Ketton solar farm - phase 2
REPD record 1772. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 3 MW
- Status
- Operational
- Operator
- Lark Energy
- County
- Leicestershire
- Region
- East Midlands
- Country
- England
- Planning authority
- Rutland
- Planning reference
- 2014/0025/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-03-17
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-01-09: Planning Application Submitted
- 2014-04-25: Planning Permission Granted
- 2014-08-01: Under Construction
- 2015-01-10: Operational
- 2019-04-25: Planning Permission Expired