Bullen Lane, Bramford - Battery Energy Storage
REPD record 17754. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 400 MW
- Status
- Planning Permission Granted
- Operator
- Clearstone Energy Limited
- County
- Suffolk
- Region
- Eastern
- Country
- England
- Planning authority
- Mid Suffolk
- Planning reference
- DC/24/05090
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-04-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-11-21: Planning Application Submitted
- 2025-03-27: Planning Permission Granted
- 2029-03-27: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 17754. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.