Bullen Lane, Bramford - Battery Energy Storage

REPD record 17754. Status: Planning Permission Granted.

Facts

As published by REPD, release Q3 2026.

Technology
Battery
Capacity
400 MW
Status
Planning Permission Granted
Operator
Clearstone Energy Limited
County
Suffolk
Region
Eastern
Country
England
Planning authority
Mid Suffolk
Planning reference
DC/24/05090
Turbines
not held by REPD
Turbine size
not held by REPD
Record last updated in REPD
2025-04-04

Status history

Dated status events as published by REPD, release Q3 2026.

Open this area on the map

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 17754. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.