slava.energy: UK renewable energy projects
Hollywood Bowl, Aintree Oval - Solar Photovoltaics Panels
REPD record 17762. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.3 MW
- Status
- Planning Permission Granted
- Operator
- Hollywood Bowl Group (Head Office)
- County
- Cleveland
- Region
- North East
- Country
- England
- Planning authority
- Middlesbrough
- Planning reference
- 24/0489/PNO
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-02-10
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-11-25: Planning Application Submitted
- 2024-12-27: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 17762. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.