A171, Guisborough Woods - Battery Energy Storage System

REPD record 17983. Status: Planning Permission Granted.

Facts

As published by REPD, release Q3 2026.

Technology
Battery
Capacity
28 MW
Status
Planning Permission Granted
Operator
a private individual (name not shown)
County
Cleveland
Region
North East
Country
England
Planning authority
Redcar and Cleveland
Planning reference
R/2025/0456/FFM
Turbines
not held by REPD
Turbine size
not held by REPD
Record last updated in REPD
2026-05-19

Status history

Dated status events as published by REPD, release Q3 2026.

Open this area on the map

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 17983. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.