slava.energy: UK renewable energy projects
Royle Gardens & Electricity Substation, Eastcotts Road - Battery Storage
REPD record 18011. Status: Planning Permission Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 0.2 MW
- Status
- Planning Permission Refused
- Operator
- AMP Energy Services Limited
- County
- Bedfordshire
- Region
- Eastern
- Country
- England
- Planning authority
- Bedford
- Planning reference
- 25/00203/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-04-23
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-01-29: Planning Application Submitted
- 2025-03-31: Planning Permission Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 18011. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.