slava.energy: UK renewable energy projects
Port of Barry
REPD record 1802. Status: Revised.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 10 MW
- Status
- Revised
- Operator
- Associated British Ports (ABP)
- County
- South Glamorgan
- Region
- Wales
- Country
- Wales
- Planning authority
- Vale of Glamorgan
- Planning reference
- 2014/01089/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-08-28
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-09-18: Planning Application Submitted
- 2014-12-19: Planning Permission Granted
- 2019-12-19: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1802. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.