slava.energy: UK renewable energy projects
Warren Farm, Masbury - Wind Turbine
REPD record 18071. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 0.33 MW
- Status
- Planning Permission Granted
- Operator
- Constantine Group Limited
- County
- Somerset
- Region
- South West
- Country
- England
- Planning authority
- Somerset
- Planning reference
- 2024/1807/FUL
- Turbines
- 1
- Turbine size
- 0.33 MW
- Record last updated in REPD
- 2025-12-16
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-01-29: Planning Application Submitted
- 2025-11-28: Planning Permission Granted
- 2028-11-28: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 18071. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.