Thames Way, Northfleet - Battery Energy Storage
REPD record 18128. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 100 MW
- Status
- Planning Permission Granted
- Operator
- Speedgreen Limited
- County
- Kent
- Region
- South East
- Country
- England
- Planning authority
- Gravesham
- Planning reference
- 20250730
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-09-03
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-08-14: Planning Application Submitted
- 2026-07-20: Planning Permission Granted
- 2029-07-20: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 18128. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.