East Lenham Solar Farm
REPD record 1816. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 6.6 MW
- Status
- Operational
- Operator
- Laurence Associates
- County
- Kent
- Region
- South East
- Country
- England
- Planning authority
- Maidstone
- Planning reference
- 12/0013
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-09-29
Status history
Dated status events as published by REPD, release Q3 2026.
- 2010-11-01: Planning Permission Expired
- 2012-01-20: Planning Application Submitted
- 2012-11-01: Planning Permission Granted
- 2014-02-01: Under Construction
- 2014-03-30: Operational
Open this area on the map