Carloggas Farm Solar Park
REPD record 1824. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 8.3 MW
- Status
- Operational
- Operator
- Good Energy Generation
- County
- Cornwall
- Region
- South West
- Country
- England
- Planning authority
- Cornwall
- Planning reference
- PA13/06288
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-08-23
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-07-18: Planning Application Submitted
- 2013-10-29: Planning Permission Granted
- 2014-10-01: Under Construction
- 2015-03-17: Operational