Parker Place, Firs Industrial Estate, Unit 8 - Solar PV array
REPD record 18253. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.27 MW
- Status
- Planning Permission Granted
- Operator
- SNRG
- County
- Worcestershire
- Region
- West Midlands
- Country
- England
- Planning authority
- Wyre Forest
- Planning reference
- 25/0125/PNO
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-05-06
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-02-18: Planning Application Submitted
- 2025-04-10: Planning Permission Granted