slava.energy: UK renewable energy projects
Somerton Door Farm
REPD record 1836. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 8.7 MW
- Status
- Operational
- Operator
- Lightsource Renewable Energy
- County
- Somerset
- Region
- South West
- Country
- England
- Planning authority
- Somerset
- Planning reference
- 14/00876/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-05-14
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-03-05: Planning Application Submitted
- 2014-06-02: Planning Permission Granted
- 2014-08-18: Under Construction
- 2015-03-01: Operational
Open this area on the map
Other REPD records on the same site
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1836. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.