Parkview solar park
REPD record 1846. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 6.5 MW
- Status
- Operational
- Operator
- NextEnergy
- County
- Devon
- Region
- South West
- Country
- England
- Planning authority
- South Hams
- Planning reference
- 50/1623/14/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-08-24
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-06-26: Planning Application Submitted
- 2014-10-28: Planning Permission Granted
- 2015-02-01: Under Construction
- 2015-03-31: Operational
- 2017-10-28: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1846. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.