Hagshaw, Conexus West -Battery Energy Storage System
REPD record 18499. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 500 MW
- Status
- Planning Permission Granted
- Operator
- 3R Energy Solutions Limited
- County
- Strathclyde
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Scottish Government (S36)
- Planning reference
- ECU00006107
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-10-05
Status history
Dated status events as published by REPD, release Q3 2026.
- 2026-05-12: Planning Application Submitted
- 2026-07-30: Planning Permission Granted
- 2031-07-30: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 18499. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.