slava.energy: UK renewable energy projects
Lower Basset Down Farm
REPD record 1850. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 10.5 MW
- Status
- Operational
- Operator
- INRG Solar
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Swindon
- Planning reference
- S/14/0899
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-03-22
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-06-20: Planning Application Submitted
- 2014-12-03: Planning Permission Granted
- 2015-11-20: Under Construction
- 2016-03-18: Operational
- 2017-12-03: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1850. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.