Keens Farm
REPD record 1871. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5.1 MW
- Status
- Appeal Refused
- Operator
- Juwi Renewable Energies
- County
- Devon
- Region
- South West
- Country
- England
- Planning authority
- Mid Devon
- Planning reference
- 12/01522/MFUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2014-08-05
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-11-07: Planning Application Submitted
- 2013-02-06: Planning Permission Refused
- 2014-07-08: Appeal Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1871. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.