slava.energy: UK renewable energy projects
Eveley Farm
REPD record 1873. Status: Revised.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 49 MW
- Status
- Revised
- Operator
- Kronos Solar
- County
- Hampshire
- Region
- South East
- Country
- England
- Planning authority
- Test Valley
- Planning reference
- 13/02735/FULLS
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-09-30
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-12-11: Planning Application Submitted
- 2014-08-15: Planning Permission Refused
- 2014-11-26: Appeal Lodged
- 2015-07-01: Appeal Withdrawn
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1873. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.