slava.energy: UK renewable energy projects
The Rainbows Solar Farm
REPD record 1876. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 4 MW
- Status
- Operational
- Operator
- Innogy (previously BELECTRIC Solar)
- County
- Gloucestershire
- Region
- South West
- Country
- England
- Planning authority
- Cotswold
- Planning reference
- 13/00578/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-02-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-02-12: Planning Application Submitted
- 2013-03-25: Planning Permission Refused
- 2013-06-13: Appeal Granted
- 2013-06-13: Planning Permission Granted
- 2014-03-31: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1876. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.