slava.energy: UK renewable energy projects
Hillsmoor Solar Farm
REPD record 1884. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1.2 MW
- Status
- Operational
- Operator
- Mosscliff Environmental
- County
- Devon
- Region
- South West
- Country
- England
- Planning authority
- West Devon
- Planning reference
- 00765/2014
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-08-16
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-06-27: Planning Application Submitted
- 2014-10-31: Planning Permission Granted
- 2017-05-15: Under Construction
- 2017-07-27: Operational
- 2017-10-31: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1884. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.