Tick Fen Farm, Puddock Road - Wind Turbine
REPD record 18979. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 0.5 MW
- Status
- Planning Permission Granted
- Operator
- Whittome Renewables Limited
- County
- Cambridgeshire
- Region
- Eastern
- Country
- England
- Planning authority
- Huntingdonshire
- Planning reference
- 25/00844/FUL
- Turbines
- 1
- Turbine size
- 0.5 MW
- Record last updated in REPD
- 2025-07-29
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-05-21: Planning Application Submitted
- 2025-07-16: Planning Permission Granted
- 2028-07-16: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 18979. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.