Thornton Estate - Solar PV Panels
REPD record 19007. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 49.99 MW
- Status
- Planning Permission Granted
- Operator
- Stark Energy
- County
- Buckinghamshire
- Region
- South East
- Country
- England
- Planning authority
- Buckinghamshire
- Planning reference
- 25/02132/APP
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-10-07
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-07-23: Planning Application Submitted
- 2026-07-10: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 19007. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.