slava.energy: UK renewable energy projects
Wilbees Farm
REPD record 1922. Status: Revised.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 7 MW
- Status
- Revised
- Operator
- Hive Energy
- County
- East Sussex
- Region
- South East
- Country
- England
- Planning authority
- Wealden
- Planning reference
- WD/2014/0436/MEA
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2014-07-29
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-03-13: Planning Application Submitted
- 2014-06-02: Planning Permission Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1922. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.