Manor Farm (Wiltshire)
REPD record 1923. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 6.3 MW
- Status
- Operational
- Operator
- RB & T Barton Ltd
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Wiltshire
- Planning reference
- 14/03084/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-03-16
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-03-17: Planning Application Submitted
- 2014-12-23: Planning Permission Granted
- 2015-03-01: Under Construction
- 2015-08-01: Operational
- 2017-12-23: Planning Permission Expired