Oaklands Farm
REPD record 1925. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 6.9 MW
- Status
- Operational
- Operator
- Lightsource Renewable Energy
- County
- Kent
- Region
- South East
- Country
- England
- Planning authority
- Ashford
- Planning reference
- 14/00326/AS
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-05-19
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-03-24: Planning Application Submitted
- 2014-06-20: Planning Permission Granted
- 2014-11-04: Under Construction
- 2015-03-30: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1925. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.