Oakwood Farm
REPD record 1929. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Abandoned
- Operator
- Bowler Energy
- County
- Buckinghamshire
- Region
- South East
- Country
- England
- Planning authority
- Buckinghamshire
- Planning reference
- 14/00615/APP
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-10-25
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-03-05: Planning Application Submitted
- 2014-12-05: Planning Permission Granted
- 2017-12-05: Planning Permission Expired