slava.energy: UK renewable energy projects
Errol Estate
REPD record 1930. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 13 MW
- Status
- Operational
- Operator
- Elgin Energy EsCo
- County
- Tayside
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Perth and Kinross
- Planning reference
- 14/00353/FLL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-06-21
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-03-17: Planning Application Submitted
- 2014-06-12: Planning Permission Granted
- 2015-12-07: Under Construction
- 2016-03-19: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1930. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.