slava.energy: UK renewable energy projects
Chittering Solar Farm - extension 2
REPD record 1939. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 9.6 MW
- Status
- Planning Permission Granted
- Operator
- Abbey Renewables (North Fen Solar Energy)
- County
- Cambridgeshire
- Region
- Eastern
- Country
- England
- Planning authority
- South Cambridgeshire
- Planning reference
- S/1331/14/FL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2019-05-16
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-06-09: Planning Application Submitted
- 2015-06-16: Planning Permission Granted
- 2018-06-16: Planning Permission Expired
Open this area on the map
Other REPD records on the same site
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1939. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.