Blaen Bowi
REPD record 1941. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5.7 MW
- Status
- Planning Permission Expired
- Operator
- Novus Solar Developments
- County
- Dyfed
- Region
- Wales
- Country
- Wales
- Planning authority
- Carmarthenshire
- Planning reference
- W/26003
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-07-18
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-01-18: Planning Application Submitted
- 2012-02-24: Planning Permission Granted
- 2017-02-24: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1941. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.