slava.energy: UK renewable energy projects
Meadowville, Hull Road - Battery Energy Storage System
REPD record 19424. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 48 MW
- Status
- Planning Permission Granted
- Operator
- UK Battery Storage Limited
- County
- North Yorkshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- York
- Planning reference
- 25/01435/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-12-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-07-29: Planning Application Submitted
- 2025-10-23: Planning Permission Granted
- 2028-10-23: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 19424. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.