Morris Marble Works, Cross Lane - Battery Energy Storage
REPD record 19439. Status: Planning Application Withdrawn.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 100 MW
- Status
- Planning Application Withdrawn
- Operator
- Bluefield Renewable Developments Limited
- County
- Tyne And Wear
- Region
- North East
- Country
- England
- Planning authority
- Gateshead
- Planning reference
- DC/25/00366/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-12-16
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-07-23: Planning Application Submitted
- 2025-12-04: Planning Application Withdrawn