Butterfly Lane, Elstree BESS - Battery Energy Storage System
REPD record 19441. Status: Appeal Lodged.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 99.9 MW
- Status
- Appeal Lodged
- Operator
- Greenfield Energy Developments Limited
- County
- Hertfordshire
- Region
- Eastern
- Country
- England
- Planning authority
- Hertsmere
- Planning reference
- 25/1070/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-06-08
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-07-18: Planning Application Submitted
- 2026-03-31: Appeal Lodged
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 19441. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.