slava.energy: UK renewable energy projects
Yew Tree Farm, Yew Tree Lane - Solar Farm
REPD record 19452. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 49.99 MW
- Status
- Planning Permission Granted
- Operator
- Yew Tree Farm Solar Limited
- County
- Somerset
- Region
- South West
- Country
- England
- Planning authority
- North Somerset
- Planning reference
- 25/P/1418/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-11-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-07-24: Planning Application Submitted
- 2025-10-08: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 19452. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.