Chisbon Solar Farm (Frowick Lane)
REPD record 1950. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 13 MW
- Status
- Operational
- Operator
- ESCO NRG
- County
- Essex
- Region
- Eastern
- Country
- England
- Planning authority
- Tendring
- Planning reference
- 13/00360/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-05-19
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-05-08: Planning Application Submitted
- 2013-07-26: Planning Permission Granted
- 2014-11-15: Under Construction
- 2015-03-05: Operational
- 2018-07-26: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1950. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.